Class Schedule
Warning: This schedule is subject to change
without notice! Watch your e-mail for updates.
- Week 1: January 13 - 15
- Week 2: January 20 - 22
- Week 3: January 27 - 29
- Week 4: February 3 - 5
- Week 5: February 10 - 12
- Week 6: February 17 - 19
- Week 7: February 24 - 26
- Week 8: March 3 - 5
- Class
- Very Preliminary Project 3 ideas presented in class
- Project 2 part B - Manufactured toys presented in class
- Assignments
- Portfolios due for mid-semester check
- Completed toy (or valiant attempt) from Project 2 due
- March 9 - 13 Spring Break
- Week 9: March 17 - 19
- Class
- Prelimninary Project 3 idea
presentation
- Egg drop
- Assignments
- Project 2 part B - Web report on toy manufacturing process due
- Week 10: March 24 - 26
- Class
- Assignments
- Proof of Concept for Project 3 due
- Revise/improve activity based on class feedback
- Week 11: March 31 - April 2
- Class
- Exercise 2
- Presentation of first functional prototypes for Project 3
- Assignments
- Self critique of Design Exercise 1 presentation due
- Register for Meeting of the Minds
- Revise/improve activity based on tester feedback
- Saturday April 4: Moving 4th into Engineering
- Week 13: April 6 - April 9
- Class
- Project 3 progress reports
- Project 3 testing
- Assignments
- First draft of Project 3 student activity sheet due
- Week 14: April 14
- April 16 -17 Spring Carnival
- Week 15: April 21 - April 23
- Class
- Project 3 presentations
- Second set of testers
- Assignments
- Fully functional Project 3 prototype due
- Week 16: April 28 - 30
- Class
- Assignments
- Project web site and complete documentation due
- Complete project due Thursday May 4
- Final Portfolio due
- Wednesday May 6
sfinger@ri.cmu.edu
|