Furnishing Copies of Plans to Municipal Client
Case Citations: NONE
Engineer "A" was retained by a municipality in 1956 to prepare plans and specifications for a comprehensive sanitary sewer program. After approximately 80 percent of the total project was constructed in subsequent years Engineer "A's" contract was terminated and he was paid in full for his services.
In 1966 the municipality retained Engineer "B" to revise and update the 1956 plans and specifications to meet current conditions. The municipality requested Engineer "A" to provide it with originals or copies of the 1956 plans and specifications which he has in his possession, offering to pay Engineer "A" for the cost of reproduction. Engineer "A" refused to comply with the request. The 1956 contract was silent as regards ownership of the plans and specifications, but did contain the following clause:
"If the City requires more than six complete sets of final plans, specifications and documents, the Engineers agree to provide any number of additional copies for no more than blueprinting, mimeographing and mailing costs".
Was Engineer "A" unethical in refusing to provide the originals or copies of the 1956 plans to the municipality?
Whether the municipality could legally require Engineer "A" to furnish the originals or copies of the 1956 plans is outside of our purview, but it may be noted that generally, in the absence of a contract provision on ownership of plans, the plans and other contract documents are the property of the client.
Engineer "A's" refusal to cooperate will put the municipality to unnecessary additional expense to the extent that Engineer "B" is required to expend additional time to investigate the work done under the 1956 contract as related to the new work to be performed. We believe that this situation is not in accord with the mandate of Code 2(a) in that Engineer "A" is not regarding his duty to the public welfare as a paramount consideration.
Under the 1956 contract, Engineer "A" was obligated to furnish additional copies of the plans to the client upon request. The fact that the contract is now terminated, regardless of the legal position of the parties, should not be used by him as a means of technical avoidance of his ethical obligation to serve the interests of the client without any cost to Engineer "A". This ethical duty is supported by the dictate of Code 1.
Engineer "A" was unethical in refusing to provide the originals or copies of his 1956 plans to the municipality.
BOARD OF ETHICAL
REVIEW CASE REPORTS
The board of Ethical Review was established to provide service to the membership of the NSPE by rendering impartial opinions pertaining to the interpretation of the NSPE code of ethics.
BOARD OF ETHICAL REVIEW
T. C. Cooke, P.E., C. C. Hallvik, P.E., James Hallett P.E., N. o. Saulter, P.E., Sherman Smith P.E., Kurt P. Wendt, P.E., Waldemar S. Nelson, P.E., Chairman.
[Disclaimer]