Date: Thu, 21 Sep 2000 01:19:00 -0700 (PDT)
From: john.hodge@enron.com
To: julie.gomez@enron.com, scott.neal@enron.com, brad.mckay@enron.com,
chris.germany@enron.com, stephanie.miller@enron.com,
sean.boyle@enron.com, colleen.sullivan@enron.com
Subject: MarketLink Shippers

Transco filed service agreements with the FERC for MarketLink (Leidy - Zone
6) yesterday.  The project will start in two phases.  The shippers and phases
are as follows:


Phase I (11/1/01 start)

Aquila Energy Marketing    25,000 Dthd
Consolidated Edison     30,000
ConEdison Energy     10,000
St. Lawrence Cement       1,000
Williams Energy Marketing  100,000

Total Phase I    166,000 Dthd

Phase II (11/1/02)

Virginia Power Energy Marketing 100,000 Dthd
PPL Energy Plus     30,000

Total Phase II    130,000 Dthd

Transco says that the remainder of the FERC-approved 700,000 Dthd project
will be phased in by 11/1/04.
The first phase will start construction in 4/01 and involves looping 30 miles
of pipe in Pennsylvannia and 30 miles of pipe in New Jersey at a cost of $123
MM. The second phase will cost $119 MM.  I will let you know the primary
delivery points of the shipper's capacity when I see the filing.