| Date | Category | Details | Time Spent |
| Wed, May 10 | Writing Reports / Presentations | Finished up writing for the phaseIII presentation. So much information to cram in a small space. | 2:00 | |
| Wed, May 10 | Writing Reports / Presentations | Started graduate credit report. reflections paper on the course long semester. | 2:00 | |
| Tue, May 9 | Writing Reports / Presentations | Made a first cut at my writing sections for the Phase-III presentation. Almost done woo-hooo! | 4:00 | |
| Wed, May 3 | Coding | watched the more groups presentation. good stuff, they blew the trinetra presenters away. | 1:20 | |
| Mon, May 1 | Class | demo!
woo hoo. too bad it didnt' go a little better. the presentation seemed
long and floundered a bit, and the transportation demo was off key. | 1:20 | |
| Mon, May 1 | Group Meeting | preperation for the demos in class. got everything set up and running. | 2:00 | |
| Thu, Apr 27 | Coding | Finalized and froze code base for Mondays presentation. All parts are in place. | 6:00 | |
| Thu, Apr 27 | Group Meeting | Demo Dry Run. OCR didn't show, big surprise. | 1:00 | |
| Wed, Apr 26 | Class | airplane comp!... omg fun and scary that we won. don't sniff glue =P | 1:30 | |
| Wed, Apr 26 | Coding | finished
integration. capacity, user display, eta, both notifications complete.
looks good. need to tie up loose ends before demo at 4:30pm. | 8:30 | |
| Tue, Apr 25 | Coding | futher
work with the eta/notification/server-client code. getting closer. gave
chris sample datasets and a small tcp client/server program to build
the graphics on top. | 6:00 | |
| Mon, Apr 24 | Class | class, talked about demo, got update from transportation group, broke off to the cic to work on integration | 1:20 | |
| Sun, Apr 23 | Coding | Integration meeting and coding session. 11am - 6:30pm 9:30pm - 12:15pm.
i'm leading the bulk of the C++ integration work. Its a real pain. | 10:15 | |
| Fri, Apr 21 | Coding | shuttle client/server. Finished WAV announcements per stop. setup the demo scenario, unit tested with perstop data. Looks Good! | 4:00 | |
| Wed, Apr 19 | Class | review and discuss the project direction and action items. everything seems on track for saturdays integration meeting. | 1:30 | |
| Wed, Apr 19 | Administrative Tasks | had
to track down phones for billing purposes. someone in our midst is a
cheat and tried to jack the phones billing information. sigh. | 0:30 | |
| Mon, Apr 17 | Class | showed jovan and joe code segments of the shuttle input handler. | 1:00 | |
| Mon, Apr 17 | Coding | finished client side application protocol. need to finish garmin api and now some type of demo functionality for dan. | 6:00 | |
| Thu, Apr 13 | Coding | Finished
application protocol, and server side implementation is done. need to
finish data classes for handling client inputs on the shuttle input
handler. need to finish client side implementation of application
protocol. | 2:30 | |
| Wed, Apr 12 | Coding | Worked on application protocol from shuttle clients to the shuttle input handler. almost finished. | 2:00 | |
| Wed, Apr 12 | Class | met with transportation group to talk about implementation progress and how our respective interfaces hook-up. | 1:20 | |
| Tue, Apr 11 | Coding | started
working on the shuttle input handler and server applications today.
made good progress, finished all of the networking code (i.e. heavily
concurrent multiplexed i/o server with priority based batch processing
for inputs) this is turning out to be some meaty code. | 8:00 | |
| Mon, Apr 10 | Class | received grades for phaseII. worked with group to review implementation progress. | 1:20 | |
| Thu, Apr 6 | Preparing Specs | rewrote part of the system design so we can proceed with implementation. | 3:00 | |
| Thu, Apr 6 | Group Meeting | 430-530. more handholding. hopefully we'll start implementation soon. | 1:00 | |
| Wed, Apr 5 | Class | class.
argued more about implementation details. having troubles solidifying
the final BL and sql tables that drive the application. | 1:30 | |
| Mon, Apr 3 | Writing Reports / Presentations | more work with phase-II document. almost finished | 4:00 | |
| Mon, Apr 3 | Class | class. talked about report, and planning for implementation. | 1:20 | |
| Mon, Apr 3 | Writing Reports / Presentations | finished report. added jovans section. | 0:30 | |
| Sun, Apr 2 | Writing Reports / Presentations | second meeting with phase-II editors. compiled results and worked on report. long meeting. | 6:00 | |
| Thu, Mar 30 | Group Meeting | first meeting with phase-II editors. assigned action items and outlined report. | 1:00 | |
| Thu, Mar 30 | Writing Reports / Presentations | Prepared template for written report. | 1:00 | |
| Wed, Mar 29 | Class | aircrafts presentation. | 1:20 | |
| Wed, Mar 29 | Administrative Tasks | kiva updates and meeting planning. | 0:30 | |
| Wed, Mar 29 | Writing Reports / Presentations | first pass at transportation written report, and yes this is pretty tedious. | 3:30 | |
| Tue, Mar 28 | Administrative Tasks | More corridination for Phase-II written report. See kiva posts. | 1:00 | |
| Mon, Mar 27 | Writing Reports / Presentations | Created phase-II report outline for transportation. Issued writting assignments to my subgroup. Kiva catchup. | 1:00 | |
| Thu, Mar 23 | Group Meeting | more presentation work. compiled slides and started BL sections to bring middle tier server together. | 2:00 | |
| Thu, Mar 23 | Writing Reports / Presentations | designed overall software architecture and server software architure slides. | 3:00 | |
| Thu, Mar 23 | Administrative Tasks | kiva catchup and worklog monitoring. | 0:15 | |
| Wed, Mar 22 | Class | Egg
Drop review session and design discussion. Assigned ownership to
presentation pieces and discussed layout of slideware. Merged into a
longer group meeting. | 3:00 | |
| Wed, Mar 22 | Administrative Tasks | kiva update. posted photos and d/l slideware to finish for tomorrows 7pm meeting. | 0:30 | |
| Tue, Mar 21 | Administrative Tasks | Planning for next two weeks of class and kiva catch up. | 1:00 | |
| Mon, Mar 20 | Class | Egg Drop. We made a cone with built in egg-eject functionality | 1:30 | |
| Mon, Mar 13 | Data Migration & Restoration | Not
sure what the "Data Migration & Restoration" category means, maybe
some type of art thing? Today I spent 9 hours! creating the static
shuttle schedules for the transportation group, this includes stops,
waypoints, and intersections and thier distance and bearing information
between data points. Consider these static shuttle schedules final and
not for review =P. | 9:00 | |
| Fri, Mar 10 | Administrative Tasks | kiva review and posted pictures of previous meetings | 0:30 | |
| Wed, Mar 8 | Class | overview of smart notes. further break down of transportation group in whiteboard session | 1:20 | |
| Wed, Mar 8 | Group Meeting | whiteboard
session. reviewed architecture started on object model across system.
new action items and reallocation of human resources into slow moving
undermaned areas. | 1:00 | |
| Mon, Mar 6 | Administrative Tasks | read kiva. update kiva. with detailed design notes and product procurement tasks. | 1:00 | |
| Mon, Mar 6 | Class | reviewed
progress of subteams in detailed design. simplified design areas,
consolidated interfaces to tie together sub-components, and repurposed
human resources. | 1:20 | |
| Mon, Mar 6 | Group Meeting | reviewed
progress of subteams in detailed design. simplified design areas,
consolidated interfaces to tie together sub-components, and repurposed
human resources.
continuation of class design meeting. we ran over. | 1:00 | |
| Thu, Mar 2 | Group Meeting | reviewed two person subteams and high level objectives moving forward.
I broke out with Chris to address Software and protocols on shuttle | 1:00 | |
| Wed, Mar 1 | Class | drilled down on task assignment and ownership. broke into two person subteams for partial product ownership. | 1:20 | |
| Tue, Feb 28 | Research | priced and purchased shuttle hardware. garmin 18, xtrasys gprs pcmcia card, 2 port 120v power inverter. | 2:30 | |
| Mon, Feb 27 | Class | group meeting. and shuttle ride. tested signal strength for mobile carriers and handheld gps receiver | 1:30 | |
| Thu, Feb 23 | Group Meeting | finalized purchasing decisions. moving forward with buying items for project. | 0:45 | |
| Wed, Feb 22 | Class | student grades. updated transportation groups task dependency timeline and revamped task assignments . | 1:30 | |
| Tue, Feb 21 | Group Meeting | 2hrs!
addressed procurement concerns for the shuttle. ironed out interaction
models and assumptions for: driver to shuttle-device, shuttle-device to
driver, shuttle-device to user, user to server. Also we listed
assumptions about the interaction models that will drive future
detailed design discussions. | 2:00 | |
| Mon, Feb 20 | Writing Reports / Presentations | grrr. rewrote the transportation task dependecy graph to meet the "formatting" of the shopping group. waste of time. | 0:30 | |
| Mon, Feb 20 | Class | task depend graph. ect. | 1:40 | |
| Sun, Feb 19 | Writing Reports / Presentations | finished
(i) transportation project planning and phase-I review, (ii) worklog
summaries for all of Trinetra, and (iii) crisis mitigation for
navigation subgroups written report | 5:00 | |
| Wed, Feb 15 | Class | class. phaseI presentations. air maintenence group. | 1:20 | |
| Wed, Feb 15 | Group Meeting | discuss and assign writting topics | 0:10 | |
| Wed, Feb 15 | Administrative Tasks | kiva catchup | 0:15 | |
| Tue, Feb 14 | Administrative Tasks | kiva catchup. writing breakdown. | 1:00 | |
| Mon, Feb 13 | Writing Reports / Presentations | review phase-I presentation | 0:30 | |
| Mon, Feb 13 | Administrative Tasks | KIVA catchup | 0:30 | |
| Mon, Feb 13 | Working with client | Meet
with Priya and SGT RICCI. 10:30am to talk about campus shuttle service
and how we can work with them. Present Joe T, Drew W, Priya N, Aaron P,
SGT RICCI. | 0:30 | |
| Mon, Feb 13 | Class | class. phaseI presentations. good job guys. | 1:20 | |
| Mon, Feb 13 | Working with client | Meet
with Priya and SGT SOBAL. 6pm. Present Joe T, Pat L, Priya N, Aaron P,
SGT SOBAL. SOBAL is the maintenence guy, knows a lot about inner
workings of shuttle/escort service. | 1:00 | |
| Fri, Feb 10 | Administrative Tasks | synch up with group and project emails/kiva. | 0:30 | |
| Fri, Feb 10 | Staff / Leaders Meeting | leaders meeting. discussed finalizing Phase-I and individual subgroup reports. | 1:00 | |
| Wed, Feb 8 | Architecture Design | Software block diagram. | 1:30 | |
| Wed, Feb 8 | Writing Reports / Presentations | editor work and finalized software diagram for architecture presentation. | 1:00 | |
| Tue, Feb 7 | Group Meeting | Architecture planning and work delegation. We need to start working on "meeting" efficiency at these events. | 1:30 | |
| Fri, Feb 3 | Staff / Leaders Meeting | planning and over for next two weeks. week in review. | 1:00 | |
| Thu, Feb 2 | Group Meeting | first architecture. planning.
in attnd:
dan s
andrew w
aaron p
asim s
outcome:
two baseline architectures | 1:20 | |
| Wed, Feb 1 | Writing Reports / Presentations | first pass at PFM presentation. | 1:00 | |
| Wed, Feb 1 | Writing Reports / Presentations | finalize PFM presentation | 1:00 | |
| Wed, Feb 1 | Class | PFM presentations | 1:30 | |
| Tue, Jan 31 | Group Meeting | Product Feature Matrix Meeting. Reviewed topics. plan to meet tomorrow 9:30 to finalize items. | 1:15 | |
| Tue, Jan 31 | Research | R&D for localization protion of transportation sub group. pending results via email | 0:30 | |
| Mon, Jan 30 | Class | HCI rough draft visionary scenarios. Q&A. | 1:20 | |
| Mon, Jan 30 | Administrative Tasks | Mgmt tasks. scheduled meetings, reminded group of tasks. | 0:30 | |
| Thu, Jan 26 | Staff / Leaders Meeting | Attendance:
Aaron Paulos, Matt Lee
Location: 2225CIC
Topic:
Discussed (i) overall project direction from HCI standpoint and (ii) division of transportation group into two groups | 1:00 | |
| Thu, Jan 26 | Group Meeting | 4:30-6PM.
Full group meeting. split group into two sections, each is researching
two topics. shorter meeting with transportation only group, new group
is joe javon drew and ap. | 1:30 | |
| Wed, Jan 25 | Group Meeting | first full group trinetra meeting, and sub group break away. | 0:30 | |
| Wed, Jan 25 | Administrative Tasks | transporation group division and planning for first trasnportation group meeting. | 1:00 | |
| Wed, Jan 25 | Class | intro to kiva and project development cycles | 1:00 | |
| Mon, Jan 23 | Group Meeting | formed subgroups | 1:00 | |
| Mon, Jan 23 | Class | trinetra and dick martin's introductions | 1:20 | |
| Wed, Jan 18 | Class | first class | 1:20 | |
Time spent:Total: 176:25
Administrative Tasks: 9:00 Architecture Design: 1:30 Class: 35:50 Coding: 54:35 Data Migration & Restoration: 9:00 Group Meeting: 20:00 Preparing Specs: 3:00 Research: 3:00 Staff / Leaders Meeting: 3:00 Working with client: 1:30 Writing Reports / Presentations: 36:00 |