Late policy: 7 free late days for assignments over the entire semester (per team).  After that 10% loss of credit for the assignment per day.  Of course, your client will evaluate lateness according to his or her own standards.

Project and Sprint 1 Plan Contents

Weekly Report Contents

For any elements that duplicate something in a current project deliverable, either copy the document or point to the other deliverable.

Inspection Report

You will carry out an inspection with respect to the specified artifact, and document the process and results as follows:

Sprint Requirements and Plan Contents

Architecture and High-Level Design Contents

All artifacts should follow the guidelines discussed in the instructors 15-313 lectures on architecture.

Test Plan Contents

Final Project Presentation

Prepare a presentation to give to the class during the finals week presentation slot.  Describe what you did in the project.  Show a graph of earned value growth over the entire project.  Talk about what went well, what went poorly, and what you would do differently next time.  What software engineering techniques were most useful, and which ones weren't?  Did your risk management anticipate the problems you saw, and how could it have been done better?

Talk about how you closed out the project and delivered the results to your client, and what feedback you got.  Give a demo or show some screenshots if possible and appropriate (it may not be feasible for all groups).  Each group should prepare a 20-25 minute presentation, leaving 5-10 minutes for questions.

Individual Reflection

Project Report

Use the same format as the weekly project report, but summarize the data over the entire project.