Software Architecture Important Assignment and Project Dates


------------------------------------------------------------------------
   #      Assigned    Discuss            Due            Topic           
------------------------------------------------------------------------
   1       01/24       02/05            02/12       Objects         
   2       02/05       02/19            02/26       Pipes           
   3       02/19       03/06            03/13       Events          
   4       03/11       NONE             04/10       Formal Models   
Project    02/07       04/01, 04/03,    03/20       Design Task     
                       04/08           progress                      
                                      4/29 final                    